Colorado Air Quality Control Commission’s preliminary final action requires early closure of Craig Station Unit 3 by end of 2028, according to report

File Photo
In an announcement Friday evening, Tri-State Generation and Transmission Association will be required to close Craig Station Unit 3 by the end of 2028 following the Colorado Air Quality Control Commission’s (AQCC) preliminary final action report, which rejected the recommendation of the state’s professional staff.
The AQCC rejected a proposal by the Colorado Department of Public Health and Environment’s Air Pollution Control Division and several electric utilities, including Tri-State.
Along with the preliminary 2028 closure of Craig Station Unit 3, the AQCC’s preliminary final action also requires the early closure of Colorado Springs Utilities’ Ray D. Nixon Power Plant and Platte River Power Authority’s Rawhide Unit 1. Tri-State added that the AQCC’s preliminary final action that would force closure of facilities is unprecedented under state and federal regulations to protect visibility.
Tri-State had previously set a voluntary retirement date of Craig Station by the end of 2029, so the decision by the AQCC moves the retirement date up a year.
“Tri-State is reducing emissions, and our proposal supported visibility improvements in our national parks and wilderness areas while keeping power reliable and affordable,” said Duane Highley, CEO of Tri-State. “We responsibly set a voluntarily retirement date for Craig Station by the end of 2029, when we intend to have added 2,000 megawatts of renewable resources.
“It must be noted that Tri-State, the other utilities, and the state’s professional staff all testified that accelerated plant closures were unnecessary to achieve visibility goals, and exceed requirements to achieve reasonable progress toward achieving visibility improvements under the regulations,” Highley added. “The Colorado Air Quality Control Commission’s unprecedented preliminary final action to require the early closure of Craig Station rejected the recommendation of the state’s professional staff.”
Tri-State and Governor Jared Polis had previously announced the cooperative’s goal on Nov. 12 to reduce greenhouse gas emissions in Colorado 80% by 2030 as part of the cooperative power supplier’s transformative Responsible Energy Plan and to support statewide emissions reductions requirements.
Tri-State says it will file its Electric Resource Plan with the Colorado Public Utilities Commission on Dec. 1, 2020. Tri-State will review the AQCC’s preliminary final action made today, and the final decision, which will be considered in December
jcarney@craigdailypress.com

Support Local Journalism

Support Local Journalism
Readers around Craig and Moffat County make the Craig Press’ work possible. Your financial contribution supports our efforts to deliver quality, locally relevant journalism.
Now more than ever, your support is critical to help us keep our community informed about the evolving coronavirus pandemic and the impact it is having locally. Every contribution, however large or small, will make a difference.
Each donation will be used exclusively for the development and creation of increased news coverage.